City and County Guides

Los Angeles ADU Permit Corrections: Common Problems and How to Resolve Them

Disclaimer: The information in this article is general in nature and is not legal, architectural, engineering, zoning, or municipal advice. Requirements vary by property, jurisdiction, and project scope. Always consult qualified professionals and the applicable reviewing department for guidance specific to your situation.
Short answer: In Los Angeles, plan check ends with a list of corrections and clearances. You answer every item, revise the plans, obtain the required clearances from other departments, and return the package for LADBS to verify. The permit issues only after the corrections meet code and the clearances are in. Delays usually come from incomplete submittals, missing clearances and zoning items such as parking, setbacks and floor area. A unit legalized under LADBS’s streamlined AB 2533 process is handled differently, through inspection correction notices rather than full plan check.

Last reviewed November 8, 2026. Fees, bulletins and laws change; confirm current requirements with the department that reviews your property.

How plan check works at LADBS

LADBS describes plan check as a review of plans and calculations by a plan check engineer for compliance with the zoning and building codes. The general flow is: you submit plans and an application, LADBS screens them for completeness and decides the type of plan check, then issues corrections and clearances. You address them, LADBS verifies, and when everything is addressed it issues a ready-to-issue status or the permit. If corrections are not fully addressed, the cycle repeats. Plans for plan check are submitted through ePlanLA or in person, depending on the project.

What a correction list covers

LADBS publishes correction sheets, including one for ADUs (LADBS ADU plan check correction sheet). The categories below come from that sheet. Versions change, so use the one that applies when you submit.

  • Application and documents: a dimensioned plot plan, legal description and ownership information, separate applications for items such as grading, retaining walls, pools and fire sprinklers, and contractor documents.
  • Clearances: items such as fire lane access for larger projects, written DWP approval for work in or within 10 feet of a DWP easement, soils or grading approvals, and verification of lot records.
  • Plan content: sheet size and legibility, title-sheet data, existing and proposed floor, framing and foundation plans, sections, elevations and energy and green code notes.
  • Zoning: parking layout, setbacks, separation from the main building, access, height, hillside rules and residential floor area limits.
  • Building code: egress and emergency escape openings, smoke and carbon monoxide alarms, fire-resistive walls and openings near property lines, natural light and ventilation, ceiling heights, and sprinklers if the main dwelling has them.
  • Energy: Title 24 calculations and compliance documents on the sheet for a standard ADU permit.
  • Structure: engineer or architect stamps, foundation and lateral design, and notes for the framing.

Common problems and how they are usually resolved

ProblemTypical way to resolve it
Incomplete or hard-to-read plans, missing title-sheet dataComplete the sheets to the correction sheet’s requirements and remove notes that do not apply to the project.
Missing clearances (fire access, sewer, DWP easement)Start clearances early, track them on the Clearance Summary Worksheet, and include the approvals in the plans.
Parking, setbacks, separation or floor area do not workCorrect the site plan and calculations; where the design genuinely does not fit, a design change may be needed.
Egress, alarms, fire separationRevise openings and details, add the required alarms, and show fire-rated assemblies where distances require them.
Light, ventilation, ceiling heightRevise the drawings to show compliant openings and heights, or adjust the design.
Energy documents missingProvide the Title 24 calculations and certificate of compliance for a standard permit. LADBS states that the Energy Code is not required for projects under its AB 2533 streamlined bulletin.
Structural calculations or stamps missingEngage the licensed engineer or architect whose stamp the correction requires.
Existing conditions do not match the drawings (legalization)Re-measure and re-draw so the plans show what is actually built, then explain differences in your response.

How to respond and resubmit

  1. Read the whole correction list, including the supplemental sheets attached to it.
  2. Write a response or a sheet reference for every item, and show where on the plans each change was made.
  3. Revise the plans and calculations, and gather the clearances.
  4. Return the package as instructed. Projects reviewed through ePlanLA upload the revised plans and responses there; other submittals are verified by appointment, bringing the originally checked set, the correction sheet and the revisions.
  5. Call or email the plan check engineer if a correction is unclear. LADBS also directs you to the engineer’s supervisor for questions.
  6. Watch the clock: LADBS’s ADU correction sheet notes that plan check expires 18 months after submittal.

The permit can be issued once the corrections meet code and the clearances are obtained. Incomplete responses can cancel a verification appointment, so check the package before you send it.

If you are using the AB 2533 streamlined process

LADBS’s bulletin for unpermitted ADUs and JADUs built before January 1, 2020 does not require a full set of construction plans. Plan check confirms the documents and clearances, and the unit is then inspected. Deficiencies are issued as correction notices, and all repairs must be completed before final approval. See the AB 2533 guide.

Ways to reduce the number of rounds

  • Read the correction sheet for your project type before you submit, and check your own plans against it.
  • Make sure every sheet agrees with the others: dimensions, areas and notes.
  • Request clearances at the start, since they can take the longest.
  • Keep a log of every correction, your answer and the sheet where it appears.

Where help fits

Bryce prepares as-built drawings and permit plans and helps organize responses to plan-check comments. Licensed professionals are involved when the project requires their stamp. See plan check coordination and correction notice assistance. City approval remains with LADBS and no outcome is guaranteed.

Common Questions

How long does it take to resolve plan-check corrections?

It depends on how many items there are, whether clearances are outstanding, and the department’s workload. LADBS does not guarantee a timeline in the materials we reviewed, so ask your plan check engineer.

Do I have to redraw everything after a correction notice?

Not usually. You revise the sheets the corrections affect and respond to each item, though changes to the site plan or structure can ripple through other sheets.

What if I disagree with a correction?

Contact the plan check engineer or the engineer’s supervisor to discuss the specific item and ask for the basis.

Can I get the permit before all the corrections are done?

LADBS says the permit can be issued once the corrections meet code and the clearances are obtained.

Does plan check expire?

LADBS’s ADU correction sheet says plan check expires 18 months after submittal. Confirm the current rule with LADBS.

Official Sources

How ADU Legalization Can Help

ADU Legalization provides general information and coordination assistance to California property owners. Bryce A. Keller, a residential designer and project manager with 20+ years of design and construction experience, helps owners understand their situation, gather records, prepare as-built drawings and permit plans, and coordinate responses to city comments. Licensed professionals are involved when the project requires their work.

We are not a law firm, licensed architect, licensed engineer, or licensed contractor. We do not guarantee any permit approval or outcome. City and county departments make the final decisions.

Related Resources

Have Questions About Your California Property?

ADU Legalization helps property owners understand their situation and coordinate the legalization process.

Request a Property Review → Call 310-570-2885