What is AB 2533?
AB 2533 is a California law that created a legalization path for accessory dwelling units (ADUs) and junior ADUs (JADUs) built without permits before January 1, 2020. For a qualifying unit, it limits the reasons a city or county can deny a permit and bars penalizing the owner for having the unit. It keeps the requirement to correct conditions that threaten health and safety. It does not make an existing unit legal automatically: you still apply, and the reviewing agency decides.
AB 2533 at a Glance
- Bill: AB 2533 (Carrillo), Chapter 834, Statutes of 2024, signed September 28, 2024.
- Effective: January 1, 2025.
- Statute: Government Code § 66311.7. When AB 2533 took effect this provision was numbered § 66332; California renumbered it on January 1, 2026, so older documents may cite the earlier number.
- Applies to: unpermitted ADUs and JADUs constructed before January 1, 2020.
- Not automatic: a permit application and agency review are still required.
What AB 2533 Does for an Eligible Unit
- Limits permit denial. An agency generally may not deny a permit because the unit violates building standards or local development standards, unless correcting the violation is necessary to protect health and safety (conditions that make a building “substandard” under Health and Safety Code § 17920.3).
- No penalty for having the unit. The agency may not penalize the applicant for the unpermitted unit and must approve the permits needed to correct health and safety problems.
- Fee relief. An owner legalizing a qualifying unit generally is not required to pay impact fees or connection and capacity charges, with limited exceptions such as utility upgrades needed to meet health and safety standards.
- Optional inspection step. After an application, an agency inspector may inspect the unit for health and safety compliance and give recommendations.
- Public information. Cities and counties must tell the public about this permit option, and many post a checklist on their website.
What AB 2533 Does Not Do
- It does not approve a unit automatically. Plans alone do not make a unit permitted.
- It does not cover units built in 2020 or later. Ask the reviewing agency which process applies to a newer unit.
- It does not excuse hazards. Agencies point to examples such as outdated electrical systems, deteriorated plumbing and gas leaks.
- It applies to units that meet the state definition of an ADU or JADU, generally complete independent living facilities with provisions for living, sleeping, eating, cooking and sanitation.
- It does not remove other clearances. Depending on the property, fire access, sewer or septic, and utility easements may still need review.
Does AB 2533 Apply to an Unpermitted Garage Conversion?
It can. If the garage was converted before January 1, 2020 and the space works as an ADU or JADU, it may be eligible. The City of Los Angeles, for example, lists the conversion of a one-story garage to an ADU among the unit types in its streamlined process. A garage finished as a bedroom, office or den without independent living facilities is not automatically an ADU, and the reviewing department decides which permit path fits. See our guides on garage conversion legalization and garage conversions in Los Angeles.
How Do I Show a Unit Was Built Before 2020?
Agencies ask for dated evidence, and each decides what it accepts. Official guidance lists examples such as County Assessor records, escrow or real estate disclosure documents, and earlier building or planning records. The City of Los Angeles also lists items such as rent registration certificates, contractor bills or material receipts, utility or insurance records, code enforcement orders, and signed leases. Start collecting these before you apply.
State Law Is Statewide; the Process Is Local
AB 2533 sets the same rules across California. The forms, plans, inspections and clearances come from the city or county that reviews your property. A mailing address does not always identify that agency.
- City of Los Angeles (LADBS). LADBS issued Information Bulletin P/BC 2026-161, effective July 15, 2026, for streamlined permitting of pre-2020 unpermitted ADUs and JADUs, with optional third-party inspection and impact fee exemptions (LADBS announcement). It names examples such as one-story detached ADUs and one-story garage conversions, and it excludes some projects, for instance buildings with a basement or more than one story and certain hazard zones. Read the current bulletin for the full list, and see permit submittal in Los Angeles. Neighborhoods such as Sherman Oaks and Studio City are part of the City of Los Angeles.
- Unincorporated Los Angeles County. The Public Works Building and Safety Division runs its own AB 2533 process under Administrative Manual AM 80.12.
- Other cities. Glendale, Pasadena, San Diego and others set their own procedures. For example, the City of San Diego explains its approach in Information Bulletin 242. Ask the building department how it handles a pre-2020 unit.
How to Get Started
- Confirm the reviewing agency for your parcel (city building department, or the county for unincorporated areas).
- Pin down the construction date and gather dated records, photos and leases.
- Document what exists today: photos, measurements and, if the agency requires them, existing-condition plans.
- Read the agency’s AB 2533 checklist and ask whether it offers a pre-application inspection.
- Apply, respond to review comments, then complete corrections and inspections. Keep the final records.
What Will It Cost?
AB 2533 can reduce some government charges, but it does not set one price for every unit. Plan preparation, city plan-check and permit fees, any engineering, and construction corrections are separate parts of the budget. Bryce quotes paid work after reviewing the project; the free initial conversation does not include drawings or detailed research. See pricing and service scope.
AB 2533 Questions
Many cities and counties describe it that way. It creates a path to apply for permits for qualifying unpermitted ADUs and JADUs built before January 1, 2020, without penalty for having the unit. Corrections needed for health and safety are still required, and approval is not automatic.
No. The law covers units built before January 1, 2020. For a newer unpermitted unit, ask the city or county which permit process and standards apply.
Yes. You apply for a permit, and the agency may inspect the unit for health and safety compliance. Corrections the agency requires still need permits and inspections.
State law generally relieves owners legalizing a qualifying unit from impact fees and connection or capacity charges, with limited exceptions such as utility upgrades needed for health and safety. City plan-check and permit fees can still apply, so ask your reviewing agency.
It depends on the agency and the unit. Some agencies, such as LADBS under its streamlined process, describe a submittal that does not require full construction plans or a licensed architect or engineer just to apply. Other agencies, and any corrections the review requires, can differ.
It can, if the garage was converted before January 1, 2020 and the space is an ADU or JADU with complete independent living facilities. A garage finished as a bedroom, office or den is not automatically an ADU. The reviewing department decides which permit path applies.
How Bryce Can Help
Bryce is a Residential Designer & Project Manager with 20+ years of residential design experience. ADU Legalization prepares as-built drawings and permit plans, coordinates documentation, and helps organize responses to city plan-check comments. Licensed professionals are involved when the project requires their work. City approval and inspections remain with the reviewing agencies, and no outcome is guaranteed. This page is general information, not legal advice.
Related Help
- Can you permit an ADU that is already built?
- Steps to legalize an unpermitted ADU
- Legalize an existing garage conversion
- Existing ADU plans and permit help
- Garage conversion legalization services
- Legalizing a garage conversion in San Diego
Official Sources
- California Government Code § 66311.7 (formerly § 66332)
- AB 2533 bill history and text
- California HCD: ADU Handbook
- HCD technical assistance letter to the City of Los Angeles (2026), which notes the renumbering to § 66311.7
- LADBS Information Bulletin P/BC 2026-161
- City of San Diego Information Bulletin 242
- City of Glendale: Accessory Dwelling Units
- City of Pasadena: ADU information
Source guidance reviewed November 8, 2026. Laws and local bulletins change; confirm current requirements with the department that reviews your property.
Ask Bryce About Your Existing ADU or Garage Conversion
Start with a free initial conversation. Detailed research, plans, and permit support are quoted separately.